Kitchen Remodel 2018

On April 15, 2018  after the worship service our church held a Church Conference to vote on the Kitchen Renovation project that we have been working on for over a year.  The members present unanimously approved the project and the budget to remodel the church kitchen. Thanks were given to Marie Marsh and Faye Ward for their untiring service as Chairmen of the Bereavement Dinner Committee and the Other Meals/Special Occasions Committee. They both served as consultants to the House and Grounds Committee during the design phase of the project.

Since Marie was a little under the weather, the motion to proceed with the project was made by Faye Ward and on behalf of Marie Marsh. Thanks to all the men and women who help with dinners at FBC and we hope you have a brand new shiny kitchen very soon!

Also, thanks Tommy Emerson for your Children's Sermon topic on it is better to give than to receive, using the building fund as a focus for the message. Tommy gave all the children $1.00 which they put into a Building Fund envelope and placed in the offering plate.  Great examples for all of us!

If you are ready to contribute to the project, please mark your checks kitchen fund. There are Building Fund envelopes and pledge cards available at the church office and around the church.

Kitchen Remodel 2018

4-15-18 Motion Made for the Kitchen Remodel

 Faye Ward makes the motion to move forward on the Kitchen Remodel 4-15-18

4-15-18 Motion Made for the Kitchen Remodel

4-15-18 Tommy Teaches about Giving

 On 4-15-18 Tommy Emerson turned the children's sermon into a lesson on giving which tied into the Kitchen Renovation.
 

4-15-18 Tommy Teaches about Giving

4-17-18 Original Stage Area

 

4-17-18 Original Stage Area

4-17-18 Original Kitchen Looking Toward Sink

 

4-17-18 Original Kitchen Looking Toward Sink

4-17--18 Original Kitchen looking toward refrigerator

 

4-17--18 Original Kitchen looking toward refrigerator

4-17-18 Kitchen Wall to be Removed

 The wall containing the upper and lower cabinets will be demolished and the hall will become part of the kitchen.

4-17-18 Kitchen Wall to be Removed

5-14-18 Phase One of the Kitchen Renovation

 The Stage is destroyed

5-14-18 Phase One of the Kitchen Renovation

5-31-18 Second Door into Kitchen Closed

 This is the wall to the left when you come into the fellowship hall from outside. The sheet rock area is replacing the second door that went into the kitchen. The door is the original hall door, which will now be the main door into the kitchen

5-31-18 Second Door into Kitchen Closed

5-31-18 New Serving Area Takes Shape

 This photo is taken from the Smith and Buckner side of the fellowship hall. The area extending into the fellowship hall is the old stage area which will now be the serving area. For size perspective, the opening into the serving area is 12 feet wide.

5-31-18 New Serving Area Takes Shape

5-31-18 Hall to Fellowship Hall

 This photo is taken in the hall headed from the Sunday School area into the fellowship hall. The new construction is a new storage area which be accessed from the serving area of the kitchen. This area used to house the steps to the stage with a hand railing and a piano sat in this space

5-31-18 Hall to Fellowship Hall

6-1-18 The Plumbing raises its ugly head!

 

We always knew that the plumbing would be the unknown in the renovation project.  It has raised its ugly head.

This photo shows the kitchen floor as of noon on Friday 6-1-18. Lots of unknown pipes and questions under the floor. If you haven't written your check for the project - now would be a great time!

6-1-18 The Plumbing raises its ugly head!

6-11-18 New kitchen flooring now in place

 Great news - the plumbing drains are all connected and the concrete is poured and the kitchen is beginning to look like the vision we have for it. This photo is taken standing in the back of the "old kitchen" looking toward the "old stage area". Part of the wall is gone that was creating a hall and the door you see is the old door to the stage which has been widened 6 inches. 

6-11-18 New kitchen flooring now in place

6-11-18 New Serving Area

This photo is in the area occupied by the old stage and is looking into the new storage closet. 

6-11-18 New Serving Area

6-11-18 New Storage Closet

This  photo is taken inside the new storage closet - which is located in part of what was the hall where the steps to the stage were across from the paper products storage area.

6-11-18 New Storage Closet

8-23-18 FRP Boards in place and Tile Coming Along

The kitchen remodel project is moving along.  The FRP (fiberglass re-enforced panels) wall coverings have covered the walls in the kitchen, serving area, and new storage closet. Both the plumbing and electrical services have passed the rough in inspection by the building inspector. The exhaust hoods have been installed.  The air conditioner and heating unit for the kitchen have been ordered.  The cabinets and appliances are ordered.  The week of August 20th has seen the ceramic tile being added.  The majority of the kitchen floor has been covered and now hold the tile cutters for all the trim work.  

8-23-18 FRP Boards in place and Tile Coming Along

8-23-18 Serving Area with new tile

 The serving area is also almost covered.  Stay turned for more updates on the biggest project FBC has tackled in a while!

8-23-18 Serving Area with new tile

8-28-18 Cabinets Installed in Serving Area

 

8-28-18 Cabinets Installed in Serving Area

8-28-18 Looking in Storage Closet from serving Area

 

8-28-18 Looking in Storage Closet from serving Area

8-28-18 New Storage Closet with Shelves

 

8-28-18 New Storage Closet with Shelves

8-28-18 Serving area awaiting new countertop

 

8-28-18 Serving area awaiting new countertop

8-30-18 Appliances Delivered

 Wow - the progress is amazing!  Today the appliances were delivered, the sinks and tables have been ordered, new LED light fixtures are in place in the ceiling, and the air conditioner/heater for the kitchen is on its pad outside the kitchen.  Stay tuned for more progress. The first photograph on the first row shows the two 5 burner stoves, the double wall ovens, and the beginning work on the air. This photograph shows the new stainless steel freezer with the dishwasher (turned backwards) awaiting its installation. The existing commercial stainless refrigerator will soon return from its temporary home in the fellowship hall. 


8-30-18 Appliances Delivered

8-30-18- New Freezer and Dishwasher

This photograph shows the new stainless steel freezer with the dishwasher (turned backwards) awaiting its installation. The existing commercial stainless refrigerator will soon return from its temporary home in the fellowship hall. 

8-30-18- New Freezer and Dishwasher

8-30-18 Mini-Split Air Conditioner Unit Outside

This photo shows the new mini-split air and heat unit.  The old kitchen had a window unit and no supplemental heat.  The new unit was required due to space constraints in the ceiling of the kitchen.  The serving area will be cooled by additional vents piped from the existing air handler in the fellowship hall. The unit on the left currently serves the Prayer Room and the new unit is on the right.  

8-30-18 Mini-Split Air Conditioner Unit Outside

8-30-18 Garbage Disposals

 Just waiting on the sinks!
 

8-30-18 Garbage Disposals

9-12-18 New Countertop Arrives for the Serving Area

 

9-12-18 New Countertop Arrives for the Serving Area

9-12-18 Close-up of the Counter top in Serving Area

 

9-12-18 Close-up of the Counter top in Serving Area

9-14-18 New Triple Bowl Sink for the Kitchen

 

9-14-18 New Triple Bowl Sink for the Kitchen

9-14-18 Single Prep Sink in the Kitchen near stoves

 

9-14-18 Single Prep Sink in the Kitchen near stoves

9-14-18 New Prep Sink and Table for Coffee and Tea in Serving Area

 

9-14-18 New Prep Sink and Table for Coffee and Tea in Serving Area